Baseline and design the migration
Inventory tags, alarms, scripts, licenses, historian interfaces and retained data. Verify the supported version and virtualization matrix before selecting the target.
ARCHITECTURE EXAMPLE
An illustrative supervisory and historian modernization plan, with separate availability, recovery and data continuity checks.
For Enterprise architects · SCADA managers · Operations leaders
A facility with standalone operator stations and inconsistent historical records needs managed engineering changes, common equipment context and a tested recovery plan.
Candidate stack: AVEVA System Platform and OMI · PI Data Archive and Asset Framework · Windows Server · VMware vSphere / ESXi. Final selection depends on the actual site, supported versions, licenses and intended use.
Inventory tags, alarms, scripts, licenses, historian interfaces and retained data. Verify the supported version and virtualization matrix before selecting the target.
Plan a Galaxy repository and reusable equipment templates. Review the alarm philosophy, operator navigation and acceptance tests with operations before deployment.
Map approved PI points into AF assets, templates and units. Define Event Frame trigger rules and test event boundaries and time consistency against known examples.
Engineer application redundancy separately from hypervisor high availability. VM restart, fault tolerance, application failover and historian continuity have different behavior and prerequisites; test them individually, including backup restore and rollback.
Sanitized conceptual view. Each numbered boundary requires an approved interface; this is not an installation drawing.
No operational impact has been verified for this proposed architecture. The blueprint describes intended benefits; dated baseline and post-change measurements, the test period and acceptance by the responsible plant owner are needed before publishing them as achieved results.
Agree the baseline, test conditions, acceptance limits and evidence owners before implementation.
| Measure | Evidence to collect |
|---|---|
| Fault identification | Use repeatable trip scenarios to time detection and diagnosis against a baseline, with equivalent operator conditions. |
| Availability and recovery | Define the measurement period, outage boundaries, RTO and RPO. Test host, application, storage and interface failures; record data gaps. |
| Engineering maintenance | Time a controlled template change, regression checks, deployment and rollback on a representative equipment set. |
These deliverables would form part of an agreed engagement. This page does not establish certification, regulatory approval, guaranteed availability or an achieved operational result.